Tajikistan is not withholding water intended for Uzbekistan. Minister of Water Resources on the Rogun HPP
Minister of Water Resources Shavkat Khamraev stated that Uzbekistan receives the established volume of water from the Amu Darya. Water accumulation in the Rogun reservoir is proceeding gradually.

Currently, the Rogun HPP reservoir is planned to gradually accumulate around 1–1.5 billion cubic meters of water. The station is already partially operational and generating electricity within its existing capabilities, Khamraev reported.
According to him, the construction of the HPP will continue for at least another four to five years, and the filling of the reservoir may take until approximately 2035. Rapidly accumulating the full volume—13.3 billion cubic meters—is impossible due to safety requirements for the hydraulic structure.
The design height of the dam is 335 meters, and it currently exceeds 200 meters. Two of the six planned hydroelectric units are operational at the station; upon completion of construction, its capacity is expected to reach 3,780 MW.
For Uzbekistan, not only the volume of accumulated water is important, but also the schedule for its release throughout the year. Downstream of the Rogun HPP is the Nurek reservoir, which regulates the flow of the Vakhsh—one of the main tributaries of the Amu Darya. The project's website states that the dam is planned to be completed by 2032, and the reservoir fully filled by 2038. The reason for the discrepancy between these timelines and the minister's estimate is not specified.